УИ-15П Transistor Oven
- Capacity by metal
- steel and cast iron 3 kg; copper 10 kg; aluminum 3 kg
- Estimated power consumption
- 20,01 kW
- Operating frequency
- 1–20 kHz
- Supply voltage
- 380 V
- Drainage mechanism
- for execution
For small melts of copper, copper alloys, and gold, we select the УИ-1П…УИ-10П versions. The gold load in this series is from 1–2 to 8–10 kg; the copper mass is determined for the selected crucible. In the УИ-15П…УИ-160П series, the copper load is 10–200 kg. For brass and bronze, the alloy grade is taken into account.
An engineer will select a model for your metal and send a cost estimate.
14 models. Copper — 10–200 kg in the УИ-15П…УИ-160П series. The small series — for small copper and gold melts; we specify the alloy load according to the crucible.















The load is given per melt. The calculated power consumption serves as a guideline for the network and is not equal to the output power of the converter.
| Model | Gold, kg | Copper, kg — calculation | Food, in |
|---|---|---|---|
| УИ-1П | 1–2 | up to 0,55 | 220 |
| УИ-2П | 3–4 | up to 1,10 | 380 |
| УИ-3П | 4–5 | up to 1,95 | 380 |
| УИ-5П | 5–6 | up to 2,50 | 380 |
| УИ-8П | 6–8 | up to 5,90 | 380 |
| УИ-10П | 8–10 | up to 6,80 | 380 |
The calculation for the small series was made for a cylindrical cavity: V = π × d² × [H − (D − d) / 2] / 4. D is the outer diameter, d is the inner diameter, H is the overall height; the bottom thickness equals the wall thickness. If the dimensions are given in millimeters, the volume by this formula comes out in cubic millimeters. To convert to liters, it is divided by 1 000 000. For the calculation, a fill of 95% of the volume was assumed; the result is rounded down in steps of 0,05 kg. Densities of pure liquid metals at the melting temperature: copper 8,0 kg/L, aluminum 2,385 kg/L. The «up to…» values are calculated guidelines, not rated loads; the profile, working level, alloy, and crucible compatibility are confirmed in the specification. These masses are not automatically carried over to brass and bronze.
The numbers in the first table refer to copper. For brass and bronze, the working load is specified according to the composition and density of the alloy, the tapping temperature, and the usable volume of the crucible. For brass, zinc evaporation and the operation of local fume extraction are taken into account; the copper mode is not automatically applied to it.
For copper, the cards of the УИ-15П…УИ-160П list silicon carbide crucibles; for small gold-melting models, graphite ones. Compatibility with the exact alloy, flux, and temperature is checked before ordering. Separate crucibles are provided for different alloy groups to limit contamination of the melt. For gold and silver in the УИ-15П…УИ-160П, the load is agreed separately by version.
The cycle includes loading, melting, adjustment of the composition, holding, and pouring. A cold start and a series of melts give different times and energy consumption. Productivity is calculated for the selected metal and the tapping schedule.
In the standard configuration, one transistor converter and one agreed melting unit are supplied. The crucible material, pouring method and controls are fixed by the specification. The chiller, extraction, installation and commissioning are listed as separate items unless they are expressly included in the proposal.
The power supply input is checked against the passport of the selected version and the full load of the area. Cooling is selected based on heat removal, flow rate, pressure and coolant quality. The frequency range refers to the operation of the agreed circuit; the operator is not expected to be able to set an arbitrary frequency.
For the calculation, please provide the metal grade, the tap weight, the type of charge, the tapping temperature, the number of melts per shift, the power supply and the pouring method. UralInduktor will select the furnace, crucible and cooling, and prepare a proposal with the scope of supply and commissioning. The cost and lead time are fixed for the agreed configuration.
Standard warranty — 18 months. The availability of a specific configuration and readiness for shipment are confirmed when ordering.
For copper in the УИ-15П…УИ-160П series, loads of 10–200 kg are given. For the small УИ-1П…УИ-10П, gold ranges from 1–2 to 8–10 kg and calculated guidelines for copper at a 95% fill are given separately. The gold range refers to the configuration options of the model; the reference size for the geometric calculation of copper does not confirm the entire gold range in a single crucible. Before ordering, the drawing of the selected crucible and the working melt level are checked.
Provide the exact alloy grade, the mass of usable metal per tap, the type of returns, the pouring temperature, and the fluxes used. This makes it possible to select the crucible material and determine the working mass. For brass, local fume extraction and a mode that accounts for zinc evaporation are also agreed; values for pure copper do not replace process selection.
The calculation requires the mass of usable metal per tap, the full melting cycle and the available working time. The cycle includes loading, heating, composition adjustment, holding, pouring and preparation of the next melting. Melting loss, slag removal and the process residue are taken into account separately. The load mass in kilograms does not mean the same productivity in kilograms per hour.
Yes, after checking the temperature, flow rate and pressure of the coolant, its quality and the available cooling capacity. The simultaneous load of the converter and the melting unit, the length of the lines and the operation of interlocks are checked. The presence of a pump or chiller on site does not by itself confirm compatibility with the furnace.
The proposal lists separately the converter, melting unit, crucible, pouring method, cooling, controls, documentation and on-site work. The standard scheme contains one converter and one agreed melting unit. A second unit, a chiller, extraction, installation and commissioning are included in the supply only according to an agreed specification.
An engineer will contact you, clarify the task and suggest a solution for your production process.
A manufacturer with a complete engineering cycle: equipment selection, commissioning and service within one company.
We manufacture induction melting furnaces and heaters, shot blasting equipment, cooling systems and steel casting ladles, taking responsibility as the manufacturer.
Selection, design, delivery, installation, commissioning, training and service within one company.
We address most metallurgical and foundry production requirements, from an individual furnace to a turnkey production area.
Operating since 2014. Completed projects of varying complexity and engineers with practical commissioning experience.
Some equipment is available from stock, reducing lead times for urgent requirements.
18-month warranty on our own manufactured equipment. Ongoing post-warranty maintenance, spare parts and service.
Send us another company's proposal — we will compare the equipment list, configuration and cost.