Price on request
5–6 kg
Gold
up to 2,50 kg
Copper — calculation at 95%
up to 0,75 kg
Aluminum — calculation at 95%
26,39 kW
Estimated power consumption
  • Shipment from the warehouse — 1-3 dayShipment to Kazakhstan 3–10 days
  • Gold melting — 5–6 kg per cycle; copper and aluminum — according to the crucible calculation
  • Transistor IGBT modules, 18-month warranty — official supply from the partner plant

Description

УИ-5П is a transistor melting furnace for small batches of metal. In the gold version, the charge is 5–6 kg. For copper and aluminum, a crucible matched to the inductor and the heating mode is selected. Calculated power consumption — 26,39 kW, supply — 380 V, operating frequency — 30–80 kHz.

  • charge — gold 5–6 kg; copper up to 2,50 kg and aluminum up to 0,75 kg (calculated)
  • power supply — 380 V; calculated power consumption — 26,39 kW
  • pouring version — no tilting
  • purpose — small-batch gold melting; versions for copper and aluminum are selected according to the crucible and mode;
  • УИ-5П is officially supplied by the partner factory; warranty of 18 months.

What is УИ-5П furnace suitable for

The УИ-5П is selected according to the required metal and the mass of a single melt. Gold charge — 5–6 kg. For copper, brass, bronze and aluminum alloys, the crucible material, usable volume, matching with the inductor and the full cycle are checked. The model index does not represent a single charge for all metals.

Technical specifications

ModelУИ-5П
Capacity by metalgold 5–6 kg; copper up to 2,50 kg and aluminum up to 0,75 kg (calculated)
Gold load, kg5–6
Crucible material for goldHigh-density graphite
Dimensions of the graphite crucible for goldPer the drawing of the agreed version
Estimated power consumption, kW26,39
Power supply voltage, V380
Operating frequency, kHz30–80
Current consumption, A43
Cooling water flow rate, L/min8
Cooling water pressure, MPa0,15–0,25
Maximum coolant temperature, °C40
Overall dimensions, mm780 × 760 × 850
Weight, kg135
Convertertransistor, water-cooled
Drainage mechanismNo tilting
Standard configuration1 transistor converter + 1 melting unit
Warranty18 months
Calculated copper capacity at 95%, kgup to 2,50
Calculated aluminum capacity at 95%, kgup to 0,75

Crucible for melting gold

To melt 5–6 kg of gold, a high-density graphite crucible is used, selected according to the usable volume, alloy composition and pouring temperature. For steel, copper and other metals, the crucible material, geometry and permissible charge are selected separately; the mass of gold cannot be transferred to another metal without checking the version.

The dimensions and fit of the replacement crucible are checked against the drawing of the agreed melting unit. During selection, the inner profile, wall thickness, height and margin to the rim at the working melt level are checked.

Overall dimensions — 780 × 760 × 850 mm; weight — 135 kg. The positioning at the workplace and the pouring method are specified from the dimensional drawing of the selected version.

УИ-5П model differences

The calculated power consumption is 26,39 kW, the operating frequency is 30–80 kHz. The frequency is selected together with the geometry of the melting unit: its purpose is to ensure the operation of the matched inductor, crucible and metal. For the power network, a current of 43 A and the load of the auxiliary equipment are taken into account.

Below it in the range is the УИ-3П (4–5 kg of gold; calculated consumption 21,48 kW), above it — the УИ-8П (6–8 kg of gold; calculated consumption 31,91 kW). The comparison is made by the mass of a single tap, the full cycle time, the available power and the cost of the infrastructure.

Load values refer to the agreed combinations of converter, inductor, and crucible. Performance is not derived from a single power: the calculation includes metal, initial temperature, preparation of furnace charge, casting and maintenance time of the crucible.

Melting of copper and aluminum

Calculation for an 85 × 60 × 130 mm crucible (outer Ø × inner Ø × height): copper up to 2,50 kg, aluminum up to 0,75 kg. The cavity is assumed to be cylindrical, and the bottom thickness equals the wall thickness. Fill level — 95%; rounded down in steps of 0,05 kg. Densities of pure liquid metals at the melting point: 8,0 and 2,385 kg/L respectively. Fillets, taper and thermal expansion are not taken into account. This is a capacity guide; the working charge, melt level and crucible compatibility are confirmed for the selected alloy and version.

Separate crucibles are used for copper and aluminum, selected according to the alloy grade, fluxes, temperature and fit in the inductor. The dimensions of the gold crucible serve as initial data for selection but by themselves do not confirm the working load of another metal.

The working weight is determined from the inner profile of the crucible, the melt level and the density at the tapping temperature. The margin to the rim and the shape and volume of the charge are taken into account. The crucible material and the agreement on the melting unit are fixed in the specification.

Power supply and cooling

Supply — 380 V; current consumption — 43 A. The converter generates an operating frequency of 30–80 kHz and requires continuous liquid cooling. The calculated power consumption of 26,39 kW serves as a guide for a preliminary assessment of the power network and is not the rated output power. The cable, protection, transformer and allocated power are checked against the data sheet of the version, including auxiliary consumers. Cooling water flow — 8 L/min at a pressure of 0,15–0,25 MPa; maximum coolant temperature — 40 °C. The heat load of the whole unit and the distribution of flow among the circuits are calculated when designing the cooling system.

Switching on the heating of the УИ-5П is permitted only when the coolant flow, pressure and temperature are confirmed. Protective grounding, emergency shutdown and a switching device with a visible break are included in the connection design.

Metallurgical constraints

The result of melting depends on the dryness and purity of the furnace charge, the release temperature and the sequence of operations. The power of the converter itself does not set the ready technological mode.

For УИ-5П, the working crucible and inductor are assigned to the selected boot string. Switching to another metal is possible after checking the frequency, geometry, crucible material and risk of melt contamination. The worker and backup crucibles can pick up and supply UralInduktor.

Supply scope and boundaries

The standard configuration of the УИ-5П includes one transistor frequency converter and one matched melting unit. The inductor, crucible, capacitor or matching unit, liquid-cooled current leads (conductors), controls and documentation are determined by the model and the metal. A second melting unit can be supplied only as an additional version under the technical specification; one converter is not intended to power two units simultaneously. Cooling, transformer, exhaust ventilation, foundation, installation and commissioning are listed as separate lines unless they are included in the specification.

After the conclusion of the contract, we provide a passport of agreed execution and a task for the foundation and construction training. The final set of passports and operational documentation is transmitted with the equipment. The task of preparing the site does not replace the working construction documentation: its development is included in the contract separately.

  • assign for УИ-5П a reverse cooling scheme, flow control and emergency stock;
  • agree for УИ-5П crucible or lining, loading method, ladle and local hood;
  • fix the pouring version: no tilting;
  • define the set of PLC, archiving, energy metering and process control system data exchange functions for the УИ-5П;
  • confirm the metal and the actual mass of issue for УИ-5П;

Manufacturing, commissioning and service

Before delivery, the УИ-5П is checked according to the agreed program. Place, volume of load and acceptance criteria are fixed in a commercial offer or contract; the customer can participate in person or by video link. When commissioning, electrical and hydraulic connections, power configuration, technological smelting and training are checked.

Popular versions of the УИ-5П are supported in the warehouse program; if the required configuration is not available, the delivery time is from 45 calendar days. Typical compact cooling is a chiller from the same manufacturer, quoted as a separate item. The standard warranty for the unit and the chiller is 18 months. Gross Metal Engineering LLP performs installation, commissioning, training, service and repair.

Information to include in your request

To perform the calculation for the УИ-5П, the following are needed: the metal and its mass, the type and size of the charge, the tapping temperature, the number of melts per shift, the 380 V mains, the existing cooling, the required crucible and the pouring method.

Questions on selection and configuration

How to read the loads of this model

For the УИ-5П, the gold charge range is 5–6 kg and refers to the agreed configuration options. Copper up to 2,50 kg and aluminum up to 0,75 kg are calculated guide values based on the reference crucible geometry at 95% fill. These data have different status: a capacity calculation does not confirm the working charge of another version. For a specific batch of gold, the drawing and usable volume of the selected crucible are also checked.

What 95 percent filling means

The calculation assumes 95% of the volume of the cylindrical cavity, and the result is rounded down in steps of 0,05 kg. This filling level serves as a condition for estimating capacity and does not set a universal permitted melt level. The working level is assigned for a specific crucible, metal, loading method and pouring method. Fillets, taper and thermal expansion are not taken into account in this estimate.

Which metals require a separate version

For copper and aluminum, a compatible crucible and melting unit are agreed first. The frequency, material and dimensions of the crucible must match the selected metal. A confirmed load of steel or cast iron for this small model is not stated in the catalog.

Which parameters to specify when ordering

For the УИ-5П, the specification records the metal grade, the working charge and melt level, the crucible material and drawing, the pouring method, cooling and controls. The calculated consumption of 26,39 kW is used for a preliminary assessment of the power network; the final power supply requirements are taken from the data sheet of the version, taking auxiliary systems into account.

Request a competitive quotation

Send another supplier's quotation for a comparison based on our manufacturing and stock capabilities.

UralInduktor · since 2014

Solutions for your production tasks

A full cycle of work with equipment for foundry, metallurgical and machine-building enterprises.

Not sure where to start? Let's discuss your task.

Discuss your task
Benefits

In-house production. Control at every stage.

We select the components, assemble and test the equipment. We adapt the solutions to your production task.

Extended warranty
18
months
on equipment

Quality control

We check the components, assembly and units before the equipment is shipped.

Under your task

We adapt the equipment to the work area, operating mode, metal and productivity.

Service support

Diagnostics, selection of spare parts and repair work.

Our own facilities

Production, warehouse and service to support your equipment.

Selection and estimate

Get an equipment selection or a project calculation — fill in the form

An engineer will contact you, clarify the task and suggest a solution for your production process.

  • Equipment selection for your metal, operating mode and output
  • Cost, lead time and delivery arrangements
  • Response within one working day

Equipment selection and estimate request

Technical specification or equipment passport PDF, DOC, XLS, JPG or PNG, up to 10 MB
In touch with you

Let's discuss your task

  • Main contact number+7 (775) 853-40-95Sales department and engineering centre
  • Emailstasgross.ru@gmail.comResponse during the working day
  • Main office addressAstana, Saryarka district, Radisson hotel, office 4
  • Office hoursMon–Fri, 9:00–18:00GMT+5 (Astana)
Comparison of proposals

We'll compare commercial proposals
and offer our own option.

Send us another company's proposal — we will compare the equipment list, configuration and cost.